Lorne Avenue Reconstruction

Scope of the Project

This project consists of the reconstruction of Lorne Avenue, from Elgin Street to Dufferin Avenue, and includes the intersection of Elizabeth Street, in the community of Wallaceburg.

The driver behind the project is the need to replace the existing infrastructure due to condition and age, in addition to upsizing the existing storm sewer as part of upgrades to the neighbourhood stormwater collection and conveyance system which includes a new trunk sewer.

Specifically, the project includes:

  • Installing a new sanitary sewer and service connections to the property line;
  • Installing a new storm sewer system and catch basins;
  • Installing new private stormwater drain connections to the property line at each property;
  • Replacing the existing watermain, service connections, and appurtenances;
  • Reconstruction of the existing asphalt road to meet current Chatham-Kent Development Standards;
  • Replacement of driveway approaches within municipal boulevards with concrete to the sidewalk or to match existing where no sidewalk is present; and,
  • Boulevard grading and restoration.

Construction is anticipated to form part of the 2022 construction season.

Online Public Information Centre

The Municipality is holding an online Public Information Centre (PIC) to present the design to the public to provide details of the project and to obtain feedback. The PIC is presented online and in PDF format along with a comment sheet so that you can provide feedback regarding any concerns or other issues associated with the project. A link is provided below. Please provide any comments by April 15, 2022, so that your input can inform the next phase of the project.

Additional details and information can be found here: www.letstalkchatham-kent.ca

If you have any additional questions, comments, or requests, please contact a member of the project team below.

Andrew Tulk, P.Eng.

Project Manager

WT Infrastructure Solutions Inc.

(519) 400-1185

andrew.tulk@wtinfrastructure.ca


Matthew Link, A.Sc.T.

Engineering Technologist

Municipality of Chatham-Kent

(519) 360-1998

ckinfo@chatham-kent.ca

Under the Freedom of Information and Protection of Privacy Act and the Environmental Assessment Act, unless otherwise stated in the submission, any personal information such as name, address, telephone number and property location included in a submission will become part of the public record files for this matter and may be released, if requested, to any person.

Scope of the Project

This project consists of the reconstruction of Lorne Avenue, from Elgin Street to Dufferin Avenue, and includes the intersection of Elizabeth Street, in the community of Wallaceburg.

The driver behind the project is the need to replace the existing infrastructure due to condition and age, in addition to upsizing the existing storm sewer as part of upgrades to the neighbourhood stormwater collection and conveyance system which includes a new trunk sewer.

Specifically, the project includes:

  • Installing a new sanitary sewer and service connections to the property line;
  • Installing a new storm sewer system and catch basins;
  • Installing new private stormwater drain connections to the property line at each property;
  • Replacing the existing watermain, service connections, and appurtenances;
  • Reconstruction of the existing asphalt road to meet current Chatham-Kent Development Standards;
  • Replacement of driveway approaches within municipal boulevards with concrete to the sidewalk or to match existing where no sidewalk is present; and,
  • Boulevard grading and restoration.

Construction is anticipated to form part of the 2022 construction season.

Online Public Information Centre

The Municipality is holding an online Public Information Centre (PIC) to present the design to the public to provide details of the project and to obtain feedback. The PIC is presented online and in PDF format along with a comment sheet so that you can provide feedback regarding any concerns or other issues associated with the project. A link is provided below. Please provide any comments by April 15, 2022, so that your input can inform the next phase of the project.

Additional details and information can be found here: www.letstalkchatham-kent.ca

If you have any additional questions, comments, or requests, please contact a member of the project team below.

Andrew Tulk, P.Eng.

Project Manager

WT Infrastructure Solutions Inc.

(519) 400-1185

andrew.tulk@wtinfrastructure.ca


Matthew Link, A.Sc.T.

Engineering Technologist

Municipality of Chatham-Kent

(519) 360-1998

ckinfo@chatham-kent.ca

Under the Freedom of Information and Protection of Privacy Act and the Environmental Assessment Act, unless otherwise stated in the submission, any personal information such as name, address, telephone number and property location included in a submission will become part of the public record files for this matter and may be released, if requested, to any person.