Elizabeth Street & Lisgar Street Reconstruction

Scope of the Project

This project consists of the reconstruction of Elizabeth Street, from Lorne Avenue to Lisgar Street, and Lisgar Street from Elizabeth Street to Elgin Street which includes some work in the intersection of Lisgar and Elgin Street, in the community of Wallaceburg.

The driver behind the project is the need to replace the existing infrastructure due to condition and age. In addition to upsizing the existing storm sewer as part of upgrades to the neighbourhood stormwater collection and conveyance system.

Specifically, the project includes:

  • Installing a new sanitary sewer and service connections to the property line;
  • Installing a new storm sewer system and catch basins;
  • Installing new private stormwater drain connections to the property line at each property;
  • Replacing the existing watermain, service connections, and appurtenances;
  • Reconstruction of the existing asphalt road to meet current Chatham-Kent Development Standards;
  • Replacement of driveway approaches within municipal boulevards with concrete to the sidewalk;
  • Boulevard grading and restoration;
  • Replace concrete sidewalks to Municipal and Provincial Standards; and
  • Replace and install concrete curb and gutter.

Construction is anticipated to form part of the 2024 construction season.

Online Public Information Centre

The Municipality is holding an online Public Information Centre (PIC) to present the design to the public to provide details of the project and to obtain feedback. The PIC is presented online and in PDF format along with a comment sheet so that you can provide feedback regarding any concerns or other issues associated with the project. Please provide any comments by February 8, 2024, so that your input can inform the next phase of the project.

If you have any additional questions, comments, or requests, please contact a member of the project team below.

Jonathon Auckland, P.Eng.

Project Manager

WT Infrastructure Solutions Inc.

(226) 332-0789

jon.auckland@wtinfrastructure.ca


Matthew Link, A.Sc.T.

Engineering Technologist

Municipality of Chatham-Kent

(519) 360-1998

ckengineering@chatham-kent.ca

Under the Freedom of Information and Protection of Privacy Act and the Environmental Assessment Act, unless otherwise stated in the submission, any personal information such as name, address, telephone number and property location included in a submission will become part of the public record files for this matter and may be released, if requested, to any person.

Scope of the Project

This project consists of the reconstruction of Elizabeth Street, from Lorne Avenue to Lisgar Street, and Lisgar Street from Elizabeth Street to Elgin Street which includes some work in the intersection of Lisgar and Elgin Street, in the community of Wallaceburg.

The driver behind the project is the need to replace the existing infrastructure due to condition and age. In addition to upsizing the existing storm sewer as part of upgrades to the neighbourhood stormwater collection and conveyance system.

Specifically, the project includes:

  • Installing a new sanitary sewer and service connections to the property line;
  • Installing a new storm sewer system and catch basins;
  • Installing new private stormwater drain connections to the property line at each property;
  • Replacing the existing watermain, service connections, and appurtenances;
  • Reconstruction of the existing asphalt road to meet current Chatham-Kent Development Standards;
  • Replacement of driveway approaches within municipal boulevards with concrete to the sidewalk;
  • Boulevard grading and restoration;
  • Replace concrete sidewalks to Municipal and Provincial Standards; and
  • Replace and install concrete curb and gutter.

Construction is anticipated to form part of the 2024 construction season.

Online Public Information Centre

The Municipality is holding an online Public Information Centre (PIC) to present the design to the public to provide details of the project and to obtain feedback. The PIC is presented online and in PDF format along with a comment sheet so that you can provide feedback regarding any concerns or other issues associated with the project. Please provide any comments by February 8, 2024, so that your input can inform the next phase of the project.

If you have any additional questions, comments, or requests, please contact a member of the project team below.

Jonathon Auckland, P.Eng.

Project Manager

WT Infrastructure Solutions Inc.

(226) 332-0789

jon.auckland@wtinfrastructure.ca


Matthew Link, A.Sc.T.

Engineering Technologist

Municipality of Chatham-Kent

(519) 360-1998

ckengineering@chatham-kent.ca

Under the Freedom of Information and Protection of Privacy Act and the Environmental Assessment Act, unless otherwise stated in the submission, any personal information such as name, address, telephone number and property location included in a submission will become part of the public record files for this matter and may be released, if requested, to any person.

Project Work Area Elizabeth Street & Lisgar Street Reconstruction

3 months

Using the map below, drop a pin within the highlighted area to provide us with comments that pertain to the proposed project.

Feedback closes Thursday, February 8 at 4 p.m. 

Page last updated: 24 Jan 2024, 11:44 AM