Wheatley Updates

This page will act as a resource page for Wheatley's Revitalization project.


This page will act as a resource page for Wheatley's Revitalization project.


  • New Completion Deadline set for Wheatley Well Remediation

    A tentative date for the completion of well remediation in Wheatley has been pushed back until the end of June.

    During a virtual public meeting held on April 9 officials announced a reduction in the evacuation zone and provided a tentative goal of mid-to-late May for remediation of all Areas of Potential Environmental Concern (APEC) within the reduced zone.

    Although capping has commenced on the Tait well (APEC 2) near the centre of the municipal parking lot, detailed work plans for similar work on APEC 1 (the well nearest the explosion site) and APEC 3 (the well at the far end of the municipal parking lot near the intersection of Erie and Elm streets) have yet to be completed.

    Officials have said safety remains the utmost concern, noting that there were two significant releases of lower explosive limit (LEL) gas on April 22 and 23. In both cases, the systems, procedures and venting stack worked according to design.

    Work on the wells will take longer than originally thought. The process of plugging a gas well is complex. Sometimes wells that were previously plugged require that they first be drilled out and re-plugged to ensure a proper seal of the well.

    During the drilling process, various subsurface conditions could be encountered which help to inform how to proceed with the next steps and can result in changes to both timelines and the workplan.

    The mitigation work requires expert consultation and methodical actions to ensure that health and safety is maintained while completing the work to current standards, involving modern construction techniques and materials.

    Everyone on site is committed to working to resolve the issue as quickly as possible, while ensuring that the appropriate health and safety measures are taken throughout the course of the mitigation work, to protect the public and those working in and around the area.

    The Tait/APEC 2 Well has been cemented/plugged up to the bedrock surface. Plugging activities at this well did take longer than expected which has pushed the overall project timeline out, however, the work on the Tait well is expected to be completed in the very near future. The team will then move to begin plugging activities on the APEC 3 Well and then to the APEC 1 Well.

    This week the municipality sent notices to owners of some properties within the evacuation zone regarding possible structural damage and what steps would be needed for future occupancy.

    The municipality will host a virtual meeting Saturday, May 14 at 10 am to answer residents' questions.

    The meeting will be hosted on the municipality’s Facebook and YouTube channels.

  • New Completion Deadline set for Wheatley Well Remediation


    A tentative date for the completion of well remediation in Wheatley has been pushed back until the end of June.

    During a virtual public meeting held on April 9 officials announced a reduction in the evacuation zone and provided a tentative goal of mid-to-late May for remediation of all Areas of Potential Environmental Concern (APEC) within the reduced zone (see map).

    Although capping has commenced on the Tait well (APEC 2) near the centre of the municipal parking lot, detailed work plans for similar work on APEC 1 (the well nearest the explosion site) and APEC 3 (the well at the far end of the municipal parking lot near the intersection of Erie and Elm streets) have yet to be completed.

    Officials have said safety remains the utmost concern, noting that there were two significant releases of lower explosive limit (LEL) gas on April 22 and 23. In both cases, the systems, procedures and venting stack worked according to design.

    This week the municipality sent notices to owners of some properties within the evacuation zone regarding possible structural damage and what steps would be needed for future occupancy.

    The municipality will host a virtual meeting Saturday, May 14 at 10 am to answer residents' questions.

    The meeting will be hosted on the Municipality's Facebook page and YouTube channels.

  • Preparations for Plugging Tait Well

    The next step in remediation of the Tait Well in the municipal parking lot will begin during the coming week.

    The project team is planning to use downhole charges to perforate the well casing.

    This is being performed in order to create holes in the casing in order for the cement to reach all areas of the well as part of the plugging operations.

    These are industry standard procedures that are routinely and safely used in the local oil and gas industry.

    Any noise or vibration associated with the casing perforation is part of the site operations.

    Chatham-Kent Fire and Emergency Services will continue its on-site presence.

  • Additional $3.9 Million Approved for Wheatley

    The Municipality of Chatham-Kent has secured a further $3.9 million from the Ontario Ministry of Economic Development, Job Creation and Trade to support the community of Wheatley after the explosion in August of last year, bringing the total amount secured to $5.9 million.

    Downtown Wheatley business owners and co-chairs of the BIA Mike and Erika Renwick said, "we are pleased to see this additional Provincial funding distributed. We appreciate the ongoing efforts of the Municipality’s Economic Development department in their communications surrounding the funding from the province. Our hope is that these additional funds will help to alleviate some of the continued financial hardships these businesses have endured and we look forward to the continued support of the province in regard to this."

    To date, $1.97 million has been distributed amongst 30 businesses, four not-for-profit organizations and 19 commercial properties over the last several months, helping provide much-needed financial assistance while they are unable to operate.

    “We’d like to thank the businesses of Wheatley for their patience, understanding, and tenacity during this difficult process. We’d also like to thank Premier Ford and his team for their diligent efforts to get these funds released into our community,” said Chatham-Kent Mayor Darrin Canniff. “This process has shown what can be accomplished when a fluid collaborative relationship is established between municipal and provincial government.”

    The additional $3.9M is being distributed in three phases designed to assist the affected businesses with revenue losses up to August 2022, with the first disbursement taking place immediately to approved applicants.

    “Our municipality has been focusing on doing everything we can to help the affected businesses of Wheatley. We’re thankful that the province of Ontario has been at the table working with us from day one and hopefully this additional $3.9 million will help the businesses during the time it takes to open their doors again,” said Stuart McFadden, Director of Economic Development Services.

    Chatham-Kent Economic Development has been coordinating the process of fund disbursement to the displaced businesses and will continue to play a role in providing affected businesses with up-to-date information, guidance, and support.

  • Work on Wheatley Properties Under Way

    The clean-up and restoration of utilities to properties formerly in the evacuation zone in Wheatley continues this week.

    As of this morning, 14 customers have had their electricity restored and ten have had their water turned on. Three dumpsters have been placed outside the evacuation zone for the convenience of residents. At this time, residents are not being billed for water usage.

    Portable washroom facilities have been made available for residents who are working on their properties but haven't had water restored.

    Earlier this month, the evacuation zone was reduced. A map of the new zone can be found on Let's Talk Chatham-Kent/Wheatley-Updates.

    Chatham-Kent Public Works Director Ryan Brown said officials are examining data from two incidents last week involving the release of a low level of combustible gas.

    There was a release of gas Friday morning and a second release Friday night that lasted until Saturday morning. In both cases, the systems, procedures and venting stack worked according to design.

    The last release at APEC 1 happened in November of 2021.

    Brown said the incidents demonstrated the effectiveness of safety procedures in place and served as a reminder that the situation is not yet fully resolved.

    Chatham-Kent Fire Chief Chris Case said Fire and Emergency Services provided additional resources and air monitoring around the perimeter of the evacuation zone to ensure safety.

    "There are valid reasons why we have been on site non-stop since gas was detected last June," he said. "Although there was no threat to public safety on the weekend, we cannot let our guard down. We will remain in place until such time as the situation is resolved."

  • Gas Flared on Site in Wheatley

    On Friday, April 22nd, a low level of combustible gas was released at the Wheatley site. The systems, procedures and venting stack worked according to design and the gas was effectively flared off.

    Public safety continues to be our priority focus and at no point was their any danger to the public. Chatham-Kent Fire and Emergency Services provided additional resources and air monitoring around the perimeter of the evacuation zone to ensure that safety.

    A second event occurred later in the evening and steps were taken to ensure ongoing safety including igniting the flare stack to control the gas and staffing up the site for overnight observation.

    By 9:00 a.m. this morning gas levels had reduced to allow the stack to be extinguished and regular monitoring returned by the on-site team.

    “We are pleased that the mitigation equipment/procedures on-site are working exactly as planned and are confident that the current evacuation zone remains secure.”, said Ryan Brown.

  • Re-drilling of Tait Well Continuing Into The Weekend

    Re-drilling of the Tait Well is continuing today and the work will continue into the weekend. Property visits within the evacuation zone are suspended while this work is underway. Property visits will resume when feasible to do so.

    Last week the evacuation zone was reduced. Work is currently underway to restore utilities in the thirty-four properties that are no longer part of the evacuation zone.

    Those wishing to review the map showing the reduction of the evacuation zone and Canada Revenue documents for residents and business owners can be found on Let's Talk Chatham-Kent/Wheatley-Updates.

    The Municipality recognizes that many residents and businesses remain evacuated and are in need of continuing support. Case Managers and Economic Development staff are available to provide support to our residents and business owners.

    A reminder to those living and working in Wheatley:

    • Victim Services is available to provide support. For those needing assistance, contact 519-436-6630 or visit https://ckvictimservices.com/.
    • The Village Resource Centre is available to provide food, clothing and aid at 108 Talbot Street East, 226-484-1004.
    • Evacuees can call 519-351-8573 during office hours and speak to a Wheatley Crisis Case Manager. After office hours they can call 519-354-6628 and they will be assisted with access to an on-call supervisor.
  • Re-drilling of Tait Well Pausing for the Weekend

    Re-drilling of the Tait Well in the APEC 2 area in Wheatley will pause during the coming weekend to allow the contractor to assess the work done to date.

    This will allow residents in the new, smaller evacuation zone an opportunity to access their properties. Residents who want access should contact their caseworkers or call the Municipality at 3-1-1.

    The evacuation area has been reduced and restaging of fencing to the new evacuation zone has been completed.

    A map showing the reduction of the evacuation zone can be found on Let's Talk Chatham-Kent/Wheatley-Updates.

    Investigation and remediation work is continuing in the new smaller evacuation zone.

  • Evacuation Zone Reduced in Wheatley

    This morning over 190 residents participated in the hour long meeting hosted on the Municipal Facebook page, where listeners could submit questions to be answered by municipal and provincial representatives.

    Those watching learned that work on the site where a gas explosion occurred back in August 2021 has reached a stage where the evacuation zone can now be reduced. A map showing the new evacuation zone boundaries can be found on Let’s Talk Chatham-Kent/Wheatley-Updates.

    Investigation and remediation work will continue in the new smaller evacuation zone. Restaging of fencing to the new evacuation zone will begin on Wednesday April 13th beginning at the north-west corner of the evacuation zone, moving clockwise around the zone. This restaging of fencing to establish the new evacuation zone is anticipated to take a day or two.

    All residents and businesses that will have access to their properties outside the evacuation zone should reach out to their insurance companies and discuss next steps.

    Reactivation of utilities must occur before occupancy. Utility companies will be working with residents to ensure a smooth reactivation process.

    For owners of properties that remain in the evacuation zone, the Municipality will endeavour to accommodate limited access for those may want access, but only to properties that are deemed safe to enter. Access will be limited to certain periods of time when on-site conditions allow for it, based on the investigation work that is ongoing.

    The Provincial Wheatley Resident Assistance Program will continue to provide assistance for temporary accommodations during renovations as required and for all households that remain evacuated.

    Beginning Saturday afternoon, April 9th, municipal case managers will be calling each evacuated household to provide guidance and discuss their individual circumstances.

    If you would like assistance in completing a pre-inspection of your home, including an initial gas reading and visual inspection of your residence for visible hazards, please communicate this to your case manager. If you miss this opportunity, please call your case manager directly to make your request. Case managers can be reached during business hours at 519-351-8573.

    Economic Development officers will be reaching out to businesses over the coming days to discuss their individual circumstances.

    Wheatley Subscription members will receive a detailed document with information and resources that outlines the various steps for safe re-entry to properties. This information will also be made available on our website at www.chatham-kent.ca.

    We would like to remind the community, safety is the top priority for the workers on-site and the community. Air monitoring will continue to be conducted 24/7 in and around the municipal parking lot, on the perimeter of the evacuation zone and on mobile units. Residents must stay outside of the evacuation zone at all times for their safety.

    Anyone can call 311 to get updates or answers to any questions.

  • Wheatley Work to Begin Tomorrow

    An oil and gas drilling contractor is anticipated to begin re-drilling the Tait Well, located in the APEC 2 area tomorrow morning.

    Residents in the areas adjacent to the evacuation zone may hear and see things that are unfamiliar to them but are perfectly normal for an oil and gas drilling operation.

    Residents can expect to see a variety of large equipment onsite including a drilling rig, storage tanks and a flare stack. Workers will be wearing a variety of personal protective equipment including at times breathing apparatus to prevent exposure to any harmful gases. During several phases of the work, the drill rig will be using a series of air horn blasts to communicate information to workers. Controlled gas releases through the flare stack are to be anticipated. During drilling, if gas is encountered the flare stack will ignite to protect workers on-site and the community. It is possible that residents may notice odours in the air similar to previous gas releases that have occurred on site.

    Safety is the top priority for the community and for the workers on-site. Air monitoring is being conducted 24/7 in and around the municipal parking lot, on the perimeter of the evacuation zone and on mobile units. Residents must stay outside of the evacuation zone at all times for their safety.

    Municipal employees and the Fire Department will be visiting adjacent properties to answer any questions from residents. Anyone can call 3-1-1 to get updates or answers to any questions. Updates will be provided as the work progresses.

Page last updated: 03 Jul 2025, 01:55 PM